Secondary Colorado River raw water line progress
Pflugerville
Summary
The 15-mile, 42-inch water line to Lake Pflugerville should carry water by November, after the Boggy Creek bypass and pump startup issues added $352,582 in extra engineering. Deflection issues and 30-inch repairs run into March 2027.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
$352,582 in additional construction-phase engineering due to the February 2026 pipe failure.
The whole city — this line secures the raw water supply to Lake Pflugerville.